Treatment MeasuresInfiltration Trenches : Treatment Performance

The curves below show pollutant removal performance expected for infiltration systems for varying soil types. These curves are based on the Melbourne hydrological region and it is expected that different hydrological regions will result in varying treatment performances. The size of the treatment measure can be simply adjusted to ensure suitable performance in other regions throughout greater Victoria. These adjustment factors are provided in Chapter 2 of the WSUD Engineering Procedures (PDF 691kb).

These curves are the basis to the STORM tool, a web based system for assessing the performance relative to best practice objectives for TN.

Melbourne (reference site) Infiltration Systems TN Removal Melbourne (reference site) Infiltration Systems TSS Removal

The curves were derived using the Model for Urban Stormwater Improvement Conceptualisation (MUSIC) (Cooperative Research centre for Catchment Hydrology 2003).

The curves were derived assuming the systems receive direct runoff (ie no pre-treatment) and have the following characteristics:

Treatment Measure Values used in Music 3.0
  Infiltration system nodes were modelled for sand and sandy loam soil types using the following parameters:
Infiltration (Sand) TSS k:400, C*:12
TP k:300. C*:0.09
TN k:40, C*:1.0
Depth to overflow weir = 0.2m
Infiltration Rate = 360mm/hr
Overflow Weir width = 20m
Infiltration (Sandy Loam) TSS k:400, C*:12
TP k:300. C*:0.09
TN k:40, C*:1.0
Depth to overflow weir = 0.2m
Infiltration Rate = 36mm/hr
Overflow Weir width = 20m